Blowdown Rate & Feedwater

The blowdown needed to hold the boiler TDS limit, the feedwater flow, and the heat going down the drain.

Unit system

Inputs

Blowdown flow

274kg/h

Blowdown as a fraction of steam

0.0274

Details

Feedwater flow10,274 kg/h
Feedwater TDS (ppm)80
Makeup water required4,110 kg/h
Heat leaving with the blowdown53.26 kW
VerdictLow blowdown — good

Assumptions

  • Steam is taken to carry no solids. With foaming or carryover the real blowdown need is higher.
  • This is continuous blowdown. Bottom (sludge) blowdown is separate and intermittent, and is not included.

Continue with this result

Calculation report

A PDF carrying the inputs, results, assumptions and the source. A one-time code is sent to your address.

Source

  • Kütle dengesi · F·TDS_besleme = B·TDS_kazan
  • IAPWS-IF97 (R7-97) · Kazan basıncındaki doymuş su entalpisi · 2007

Results are for engineering pre-assessment and are not a product selection commitment. Final responsibility rests with the user.